Streetscape Public Notice – September 16, 2019

Daily Construction Update for Monday, September 16, 2019

On Monday, construction crews continued installing drainage on the west side of BHOP and paved additional trenches that were excavated for installation of the drainage.

Starting, today, Tuesday, September 17, 2019, construction crews will begin installing new curbing and sidewalks beginning at the intersection with Highland Street and working their way east.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 13, 2019

Daily Construction Update for Friday, September 13, 2019

On Friday, construction crews continued installing drainage along the northern side of the street, east of BHOP down towards the traffic signal. Additional drainage work will be completed on the west side of BHOP on Monday. The contractor also paved around several of the new catch basins on Friday and will continue paving on Monday.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 12, 2019

Daily Construction Update for Thursday, September 12, 2019

On Thursday, construction crews began installing drainage along the northern curb east of BHOP down towards the traffic signal. That work will continue on Friday and will require temporary closure of the on-street parking along this stretch of curb. That will complete the majority of the drainage construction.

The contractor is planning on paving around the new catch basins on Friday.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 11, 2019

Daily Construction Update for Tuesday, September 11, 2019

A new catch basin was installed Wednesday at the intersection with Chase Street. Additional construction crews installed frames and grates on all the catch basins that have been installed so far. Thursday, crews will be installing a new catch basin at the entrance to the Town parking lot just west of the Bridgton House of Pizza (BHOP). Please anticipate that this entrance into the parking lot may be closed during this construction. You can still access the parking lot via the Key Bank driveway or the entrance to the Municipal lot off Chase Street.

If time permits, they will also begin installing drainage along the northern curb east of BHOP down towards the traffic signal. This will require temporary closure of the on-street parking along this stretch of curb. That will complete the majority of the drainage construction.

The contractor is planning on paving around the new catch basins on Friday.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 10, 2019

Daily Construction Update for Tuesday, September 10, 2019

Several new catch basins and drain manholes were installed Tuesday as part of the storm drainage system upgrades throughout the project corridor.

The contractor will continue to install storm drainage upgrades throughout Main Street for the rest of this week. Some water line construction will also happen at the intersection with Church Street and in front of the Magic Lantern. That water line work will happen either at the end of this week or next week.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 9, 2019

Daily Construction Update for Monday, September 9, 2019

Several new catch basins and drain manholes were installed Monday as part of the storm drainage system upgrades throughout the project corridor.

The contractor will continue to install storm drainage upgrades throughout Main Street for the rest of this week. Some water line construction will also happen at the intersection with Church Street and in front of the Magic Lantern. That water line work will happen either at the end of this week or next week.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 6, 2019

Daily Construction Update for Friday, September 6, 2019

One new catch basin and a drain manhole were installed today as part of the storm drainage system upgrades across the street from the Rufus Porter museum

Next week there will be storm drain construction in front of the Ruby Food restaurant and the Magic Lantern. The sidewalks and a few parking spaces will be closed in both of these areas during the construction, but will reopen at the end of the day. Temporary paving will go down on the areas of the road that were dug up.

The contractor will continue to install storm drainage upgrades throughout Main Street next week. We will continue to update as the work progresses and we learn more about the detailed schedule.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Public Notice – September 5, 2019

Daily Construction Update for Thursday, September 5, 2019

Two new catch basins and a drain manhole were installed Thursday as part of the storm drainage system upgrades at the intersection with Church Street and at the intersection with Depot Street by the Magic Lantern. On Friday, some additional drainage structures will be installed in the sidewalk along the park across the street from the Rufus Porter museum and also in front of the Ruby Food restaurant. The sidewalks and a few parking spaces (by Ruby Food) will be closed in both of these areas during the construction, but will reopen at the end of the day. The contractor is also hoping to pave the road in a few spots where it has been dug up to install drainage this week.

The contractor will continue to install storm drainage upgrades throughout Main Street next week. The exact locations of where the work will happen on each day is a little tricky to forecast but we will continue to update as the work progresses and we learn more.

Colin Dinsmore, PE
HEB Engineers, Inc

Streetscape Project Notice September 3, 2019

Daily Construction Update for Tuesday, September 3, 2019

The Streetscape contractor installed a couple new catch basins as part of the storm drainage system upgrades yesterday (Tuesday) near the intersection with Highland Street and at the intersection with Cottage Street. On Wednesday, additional catch basins will be installed in front of the library and the Magic Lantern. The contractor will continue to install storm drainage upgrades throughout Main Street for the remainder of this week and next week. The exact locations of where the work will happen on each day is a little tricky to forecast but we will continue to update as the work progresses and we learn more.

Colin Dinsmore, PE