Wastewater Project Updates

Wastewater Expansion Project – Test Boring: Mon July 8 – Thurs July 11

Engineers will be completing soil borings throughout Bridgton in the roadway for proposed lines in connection with the new proposed waste water treatment facility/sewer system. They are performing shallow borings, up to 15 feet in depth in 50 locations throughout Bridgton.  Map of proposed locations may be found HERE.

• Day One – Monday, 7/8 – Start at the intersection of Oak Street and Main Street at the eastern end of the probes. Complete all of Main Street and Depot Street probes.
• Day Two – Tuesday, 7/9 – Start at the intersection of High Street and Hospital Drive. Complete High Street, Pleasant Street, Creamery Street, Fowler Street, Walker Street, & Church Street
• Day Three – Wednesday, 7/10 – Start at the intersection of Highland Road and Kennard Street. Complete Kennard, Bacon, Wayside, Nutty, Elm, Bennett, Iredale, McIntyre, & Meadow Street. Complete Frances Bell Drive if time permits.
• Day Four – Thursday, 7/11 -Start either on Frances Bell Drive or Portland Road and progress north to south.