At this time residents can expect that the roads will remain unpaved for at least the next several weeks. Sargent plans to come back through and pave each road once the sewer has been completed on multiple streets. In the areas where the water and sewer work is being done, the road will not be paved until both water and sewer work is completed.

Areas that include both water and sewer work are: Nulty Street, Church Street, Cottage Street, Gage Street, Fowler Street, Walker Street, and the area of Willet Road intersection with Route 302.

A field engineer from Woodard and Curran will be going around to each house to confirm the proposed sewer lateral location with the property owner so please be on the look-out for them. The in-person meetings with the engineer are expected to being April 23rd in the Nulty Street Area.

Click here to view the PDF Version of Map Updates for 04.26-05.07