Daily Construction Update for Tuesday, September 24, 2019

Sidewalk and curbing construction continues between Highland Street and Elm Street. The contractor has decided to continue with the sidewalk reconstruction on the north side of the road all the way down to Elm Street because several sections of the existing sidewalk have been dug up for the drainage installation. We would like to get those sections completed with the new sidewalk as soon as possible.

Light pole bases should be installed towards the end of this week or early next week. The contractor is waiting on the arrival of some additional street light infrastructure components and as soon as those arrive they can begin pouring concrete for the sidewalks.

There will be brief closures of driveways as the conduit trench crosses each driveway but the contractor will work to ensure access is restored as quickly as possible.

Colin Dinsmore, PE
HEB Engineers, Inc