Daily Construction Update for Tuesday, September 3, 2019
The Streetscape contractor installed a couple new catch basins as part of the storm drainage system upgrades yesterday (Tuesday) near the intersection with Highland Street and at the intersection with Cottage Street. On Wednesday, additional catch basins will be installed in front of the library and the Magic Lantern. The contractor will continue to install storm drainage upgrades throughout Main Street for the remainder of this week and next week. The exact locations of where the work will happen on each day is a little tricky to forecast but we will continue to update as the work progresses and we learn more.
Colin Dinsmore, PE